Commissioning & Safety
Commissioning & Safety
First-Fire / Bake-Out Schedule
Mandatory before service to drive off binder and moisture from refractory. Run empty, door cracked 20 mm, in a ventilated area.
| Step | Target | Ramp | Hold |
|---|---|---|---|
| 1 Dry | 120 °C | 40 °C/h | 4 h |
| 2 Bind burn-off | 350 °C | 40 °C/h | 2 h |
| 3 Cure | 600 °C | 60 °C/h | 2 h |
| 4 Oxide film | 1050 °C | 80 °C/h | 3 h |
| 5 Cool | ambient | natural, door shut | — |
Step 4 forms the protective alumina scale on the FeCrAl elements — do not skip. Never touch elements once fired; the oxide is brittle when cold.