Commissioning & Safety

Commissioning & Safety

First-Fire / Bake-Out Schedule

Mandatory before service to drive off binder and moisture from refractory. Run empty, door cracked 20 mm, in a ventilated area.

Step Target Ramp Hold
1 Dry 120 °C 40 °C/h 4 h
2 Bind burn-off 350 °C 40 °C/h 2 h
3 Cure 600 °C 60 °C/h 2 h
4 Oxide film 1050 °C 80 °C/h 3 h
5 Cool ambient natural, door shut

Step 4 forms the protective alumina scale on the FeCrAl elements — do not skip. Never touch elements once fired; the oxide is brittle when cold.